Milling and Paving
2nd Ave and McConnell
The Milling on 2nd Ave and McConnell began earlier this week. Paving is scheduled to begin Friday, May 15, and be completed in the next week, weather dependent. Per Town code, crews are authorized to work between 7 am and 7 pm daily. During this time, traffic will be limited to local traffic only and may experience delays of 20-30 minutes. There will be flaggers to maintain local access, but there will be wait times as the paving operation passes through the access points.
If you live along 2nd Ave. and have concerns about the 20- to 30-minute delay, we recommend you park your car outside of the paving area, so you may easily leave in your vehicle, between 7 am and 7 pm. Suggestions for parking include McConnell Dr. (northwest of the paving towards the Middle/Senior High School) or in the Waste Water Treatment Plant parking lot.
If there is a weather delay, the Town will send a new update.
Upon finishing these two streets, the crew will move to 4th and Evans curve.
All of this work is part of a large, grant funded flood recovery project will be phased and is scheduled thru July 31.
Upon finishing these two streets, the crew will move to 4th and Evans curve.
All of this work is part of a large, grant funded flood recovery project will be phased and is scheduled thru July 31.
Other streets to be completed over the next three months include 2nd Ave between Broadway and Park, and 3rd Ave, 4th Ave and Evans St. We will send out updates from the contractor on the schedule for the streets.