Milling and Paving
Evans St., 4th Ave., 3rd Ave., and 2nd Ave. | McConnell Dr. & 2nd Ave.
Beginning the week of May 11, 2020, several flood-impacted local streets will undergo important milling and paving, along with curb and gutter in some areas. This grant-funded flood recovery project will be completed in phases, as scheduled to occur from May 11 through July 31.
The first phase consists of milling and repaving along 2nd Ave. and McConnell, beginning the week of May 11. Other streets to be completed over the next three months include 3rd Ave., 4th Ave. and Evans St.
Project Communications |
Date | Type | Message | Recipients |
5/19/20 | Doorknockers | Project & Parking Notice | Evans St, 3rd Ave, 4th Ave and 2nd Ave |
5/11/20 | Doorknockers | Project & Parking Notice | Residences adjacent to McConnell and 2nd |
5/6/20 | Signs | Road Work Notice (1 and 2) | Entryways along McConnell and 2nd |
5/6/20 | Webpage | Overview of Project | Website, home page |
5/6/20 | Eblast | Overview of Project | Eblast listserv, Facebook, Twitter |
1/15/20 | Meeting | Overview/Question-Answer | Only three people attended. Received other calls and emails separately. |
Early January | Doorknockers | Notice of Meeting (1/15/20) | Residences of Evans, Second, Third, Fourth |
11/6/19 | Meeting | Overview of Project | Specific to Evans St. between 4th and Evans and surrounding streets. In this meeting the issue of traffic calming was also discussed. |
10/18/19 | Doorknockers | Notice of Meeting (11/6/19) | Specific to Evans St. between 4th and Evans and surrounding streets. In this meeting the issue of traffic calming was also discussed. |
9/24/19 | Doorknockers | Notice of project | Residences of Evans, Second, Third, Fourth |
Updates from the contractor on the streets’ schedule will be sent via Town eblast.