Safe Route to School
4th Ave Ped Bridge, Trail and Sidewalks
From Bohn Park along 4th Ave over N St Vrain Creek up to High St and Lyons Elementary School
This project includes a multi modal trail for bikes and pedestrians from Bohn Park to the N St Vrain.
A pedestrian bridge will be placed over the N St Vrain and there will be bike lanes and sidewalks from Evans St (north of the bridge) along 4th Ave up to HIgh St and the intersection of 4th Ave and High St at the Lyons Elementary School.
The project is scoped at $855,000 with the Town of Lyons receiving a $500,000 Safe Route to School (SRTS) Grant from CDOT and the balance from CBDG-DR Boulder Collaborative Flood Recovery Funds.
The project is currently in 30% design.
There is a public meeting with residents on Thursday May 13th at 6 pm. You are welcome to join us at Town Hall or zoom in if you'd prefer!
Click the zoom link and the meeting info is below
Meeting ID: 881 8617 5422
Passcode: 477418
Or call in.
+16699006833,,88186175422#
There is another public meeting on Tuesday May 18th. It will be in person at Town Hall or zoom in if you'd like to.
Construction is expected to begin in late Fall 2021 with the project completed in 2022.
The design engineers presented at the April 5, 2021 BOT workshop. View the presentation.
Updates regarding the project will also be sent via Town eblast.