Posted on: May 6, 2020

[ARCHIVED] Flood Recovery Milling and Paving

Milling and Paving

Milling and Paving 

Evans St., 4th Ave., 3rd Ave., and 2nd Ave. | McConnell Dr. & 2nd Ave.

This project includes important milling and paving, along with curb and gutter in some areas, on several flood-impacted local streets. This grant-funded flood recovery project will be completed in phases, as scheduled to occur from May 11 through July 31. Check this page for weekly updates from the contractor. 

August 25, 2020

What’s happening this week? 8/24 – 8/28 

  • Pavement striping and signage is scheduled to be completed 

What’s happening next week? 8/31 – 9/5 

  • Pipe crews are scheduled to install new storm drain on 4th Avenue between Main and Broadway 

What’s coming in the next few weeks? 

  • Asphalt removal and reconstructing the roadway subgrade on 4th between Main and Broadway is scheduled to start 
  • Asphalt placement on 4th between Main and Broadway 
  • Backfill sidewalk on 2nd Ave 
  • Place asphalt driveways on 2nd Ave 
  • Seeding 
  • Punchlist items 

Traffic Impacts – 4th Ave will be closed between Main St and Broadway starting 8/31 thru to 9/11. Pedestrian traffic will be allowed to access the businesses along 4th Ave. 

All work described is subject to change based on weather conditions and materials supply.


Project Communications

Date

Type

Message

 Recipients

5/19/20

Doorknockers

Project & Parking Notice

Evans St, 3rd Ave, 4th Ave and 2nd Ave

5/11/20

Doorknockers

Project & Parking Notice

Residences adjacent to McConnell and 2nd

5/6/20

Signs

Road Work Notice (1 and 2)

Entryways along McConnell and 2nd

5/6/20

Webpage

Overview of Project

Website, home page

5/6/20

Eblast

Overview of Project

Eblast listserv, Facebook, Twitter

1/15/20

Meeting

Overview/Question-Answer

Only three people attended. Received other calls and emails separately.

Early January

Doorknockers

Notice of Meeting (1/15/20)

Residences of Evans, Second, Third, Fourth

11/6/19

Meeting

Overview of Project

Specific to Evans St. between 4th and Evans and surrounding streets. In this meeting the issue of traffic calming was also discussed.

10/18/19

Doorknockers

Notice of Meeting (11/6/19)

Specific to Evans St. between 4th and Evans and surrounding streets. In this meeting the issue of traffic calming was also discussed.

9/24/19

Doorknockers

Notice of project

Residences of Evans, Second, Third, Fourth


Updates from the contractor on the streets’ schedule will be sent via Town eblast.