News Flash Home
The original item was published from 6/18/2020 1:39:00 PM to 6/18/2020 4:24:14 PM.

News Flash

News Blurbs

Posted on: May 6, 2020

[ARCHIVED] Flood Recovery Milling and Paving

Milling and Paving

Milling and Paving 

Evans St., 4th Ave., 3rd Ave., and 2nd Ave. | McConnell Dr. & 2nd Ave.

This project includes important milling and paving, along with curb and gutter in some areas, on several flood-impacted local streets. This grant-funded flood recovery project will be completed in phases, as scheduled to occur from May 11 through July 31. Check this page for weekly updates from the contractor. 

June 17, 2020
What’s happening this week? 6/15 – 6/20

  • Concrete crews are forming and pouring curb and gutter on Evans from 3rd Ave to 2nd Ave 
  • Concrete crews are scheduled to start pouring driveways 
  • Pipe crews are installing new storm drain along Evans Ave and 4th Ave 
  • Installation of a new waterline on 3rd Ave between Evans and Railroad is scheduled to start 
  • Asphalt removal on 3rd Ave from Railroad to Evans is scheduled to continue this week 
  • Crews are scheduled to continue backfilling behind the new curb and gutter and regrading driveways starting from 4th Ave & Park then continuing along Evans to 3rd Ave 
  • Crews are scheduled to start reconstructing the roadway subgrade at 4th Ave & Railroad then continuing on Evans Ave to 3rd Ave 

What’s happening next week? 6/22 – 6/27

  • Concrete crews are scheduled to continue to form and pour new curb and gutter on Evans from 3rd Ave to 2nd Ave 
  • Concrete crews are scheduled to continue pouring driveways 
  • Installation of a new waterline on 3rd Ave between Evans and Railroad is scheduled to continue 
  • Crews are scheduled to continue backfilling behind the new curb and gutter and regrading driveways 
  • Crews are scheduled to continue reconstructing the roadway subgrade at 4th Ave & Railroad then continuing on Evans Ave to 3rd Ave 
  • Asphalt removal on 2nd Ave from Evans to Park is scheduled to start 
  • Asphalt placement is scheduled to start this week on 4th Ave at Park and continue along Evans to 3rd Ave 

What’s coming in the next few weeks? 6/29 – 7/4

  • Concrete crews are scheduled to start to form and pour new curb and gutter & sidewalk on 2nd Ave 
  • Concrete crews are scheduled to continue pouring driveways along Evans 
  • Pipe crews are scheduled to construct modifications to the Lyons Ditch at 2nd Ave and Evans 
  • Crews are scheduled to continue backfilling behind the new curb and gutter and regrading driveways 
  • The old guardrail at the curve is scheduled to be removed at the curve and new guardrail placed after asphalt is placed 

Traffic Impacts 
With asphalt removal starting this week on 3rd Ave between Railroad and Evans no on street parking will be accommodated for this area until the project is complete. Also there may some short delays with access to the Post Office while crews work in this area and suggest to park on Railroad to access the post office. One way traffic pattern will be in place along the curve at 4th and Evans. Traffic will only be allowed to travel west/north along the curve between Park Ave to the end of the curve later this week. This is to allow safe travel through this narrow section until asphalt and striping are complete. Please adhere to the traffic signage. XXAll work described is subject to change based on weather conditions and materials supply. XThank you to all residents for their assistance with moving their vehicles and patience as we reconstruct our public roads. XAs a continued reminder, this is an active construction zone and please stay out of the roadway when work is occurring, especially children! XXSafety tip! – There are open trenches as new storm drain and waterlines are being installed. Please stay clear from the edge of the trenches as there is a fall hazard as well as the sides of the trench can cave in.

All work described is subject to change based on weather conditions and materials supply. Thank you to all residents for their assistance with moving their vehicles and patience as we reconstruct our public roads. 

As a continued reminder, this is an active construction zone and please stay out of the roadway when work is occurring, especially children! 

Safety tip! – if you have the need to enter the construction zone, please give our flaggers a heads up and they can tell you how best to stay safe. Plus it’s a boring job and they would love a quick chat!



Project Communications

Date

Type

Message

 Recipients

5/19/20

Doorknockers

Project & Parking Notice

Evans St, 3rd Ave, 4th Ave and 2nd Ave

5/11/20

Doorknockers

Project & Parking Notice

Residences adjacent to McConnell and 2nd

5/6/20

Signs

Road Work Notice (1 and 2)

Entryways along McConnell and 2nd

5/6/20

Webpage

Overview of Project

Website, home page

5/6/20

Eblast

Overview of Project

Eblast listserv, Facebook, Twitter

1/15/20

Meeting

Overview/Question-Answer

Only three people attended. Received other calls and emails separately.

Early January

Doorknockers

Notice of Meeting (1/15/20)

Residences of Evans, Second, Third, Fourth

11/6/19

Meeting

Overview of Project

Specific to Evans St. between 4th and Evans and surrounding streets. In this meeting the issue of traffic calming was also discussed.

10/18/19

Doorknockers

Notice of Meeting (11/6/19)

Specific to Evans St. between 4th and Evans and surrounding streets. In this meeting the issue of traffic calming was also discussed.

9/24/19

Doorknockers

Notice of project

Residences of Evans, Second, Third, Fourth


Updates from the contractor on the streets’ schedule will be sent via Town eblast.

Facebook Twitter Email

Other News in News Blurbs

bear_trash

Bear Resistant Trash Bins Order Info

Posted on: March 21, 2023
bear_trash

What's on Tap Lyons?

Posted on: March 10, 2023